|
Litigation Procedure
Preclusion. The agencies argued that the plaintiffs’ segmentation claims should be dismissed under the legal theories of “claim preclusion” and “issue preclusion” because the same claims had been litigated in a previous case, Save Barton Creek Association v. FHWA. The previous case concerned challenges to construction projects involving a portion of MoPac South and a planned (but never built) segment of SH 45. The court found that the Save Barton Creek case and the current case involved different facts:
[A]lthough part of the Express Lanes Project and the Intersections Project are expansions to the portion of MoPac South in Save Barton Creek, the construction projects in this case are new and are different from the construction project in Save Barton Creek. Nothing in the complaint or opinion in Save Barton Creek indicates that case encompassed, considered, or applied to future expansions of MoPac South, particularly the expansions at issue in this case. In short, the facts are not the same.
Therefore, the court held that the plaintiffs’ claims in this case were not precluded by the decision in Save Barton Creek.
Finality/Ripeness. The defendants contended that the segmentation and cumulative impact claims regarding the Express Lanes Project should be dismissed because there was no final agency action and they were not ripe for judicial review. The court held that, while the EA for the Express Lanes project was not yet final, the agencies had made a final decision to segment the three projects for purposes of environmental review, and therefore the segmentation claim was ripe for review. The court explained:
[I]t is undisputed that Defendants have made the decision to segment the three projects for purposes of environmental review and thus perform three separate environmental analyses. The dispute is whether such segmentation itself is proper, not whether the resulting environmental decisions are proper. In other words, Plaintiffs complain of Defendants’ segmentation procedure, which has already taken place. The decision to segment is not tentative. The scope of the three projects’ environmental review is set, and legal consequences will flow from this segmentation decision.
Therefore, the court held that the segmentation claim was ripe for review. The court also held that TxDOT had made a final decision to not consider cumulative impacts of the projects, because the final environmental decisions for two of the three projects had already been issued without considering cumulative impacts.
NEPA
Applicability of NEPA to State-Funded Project. TxDOT explained that it did not conduct an environmental study of the SH 45SW Project under NEPA because the project relied only on state and local funding and therefore was not a federal action that triggered NEPA. The plaintiffs contended that the SH 45SW Project was a federal action because it was potentially subject to control by USFWS due to the potential for the project to cause incidental take of endangered species. The court held that further development of the factual issues was needed before the claim could be resolved. Therefore, the court denied TxDOT’s motion to dismiss this claim, and the claim remained under consideration in the lawsuit.
|