Case Law Details
Home » City of Eufala v. Alabama DOT
City of Eufala v. Alabama DOT
Project Description:
This case involved the proposed widening of a 0.8 mile stretch of North Eufaula Avenue in Eufaula, Alabama. The court described this section of North Eufala Avenue as a “a two-lane road running through an historic district of town, with old houses lining each side and a 30-50 foot median of billowing trees that overhang the street. The street is featured in the Alabama Scenic Byway Program, which received some federal funding, and is a major source of tourism income for the city.” This section of North Eufala Avenue is part of Alabama Highway 431, a state route that runs north-south along the eastern side of the state and leads to the Gulf Coast beaches. The Alabama Department of Transportation (ADOT) was engaged in a long-term effort to widen Highway 431 to four lanes. Prior to this project, the Highway 431 widening projects (outside of Eufala) had been completed with state funds and therefore did not undergo federal environmental review. For the section of Highway 431 in Eufala, ADOT initially proposed constructing a bypass around the town. FHWA and ADOT prepared a NEPA document for the proposed bypass and FHWA issued a decision document approving it, but the bypass was never built due to community opposition. ADOT then proposed widening North Eufala Avenue to four lanes, providing a continuous four-lane section on Highway 431 directly through the town. ADOT proposed to undertake this widening project without any federal funds, and therefore did not undertake any federal environmental review for the project. At the time this lawsuit was filed, ADOT had issued a construction contract for the widening of North Eufala Avenue.
2014 WL 7369783
2014 WL 7369783
U.S. District Court – Alabama
12/29/2014
North Eufala Avenue Widening
Highway
Case Summary
On December 8, 2014, the plaintiffs filed a lawsuit against FHWA and ADOT, requesting a temporary restraining order (TRO) to prevent ADOT from beginning construction of the project on North Eufala Avenue. The plaintiffs claimed that FHWA and ADOT had violated NEPA, Section 4(f), Section 106 of the NHPA, and other federal requirements by failing to complete the federal environmental review process before beginning construction. The court found that the plaintiffs were unlikely to prevail on the merits of their claims because the federal environmental requirements do not apply to a state-funded project. Therefore, the court denied the request for a TRO.
Key Holdings
NEPA Federalization. The plaintiffs acknowledge that the North Eufala Avenue project was being built solely with State funds, but argued that the project had been “federalized” – and thus required federal environmental review – because it is part of a larger project that the federal government had helped to develop and execute. The court considered three factors in determining whether the project had been federalized: Pretext. First, the court considered whether the project had been labeled as a pretext – that is, as a means of avoiding some obstacle in the federal environmental review process. The court found that “[p]retext is not present in this case” because “Alabama did not apply for federal funds and then decide against using them once the federal government expressed reservations about its environmental-impact statement.” The court did note that “the State’s explanations that it did not want to get involved in the federal process do suggest it wanted to avoid federal-environmental standards.” But it held that the “pretext problem arises only when States obviously tip their hand that they believe a road is part of a federal project by submitting an environmental impact statement and then insist it is a state project after failing the federal standards.” Degree of Federal Involvement. Second, the court considered the degree of federal involvement in the project. The court noted that, in this case, the federal government “did not approve the location, conduct an engineering study, plan with the State, or exercise other forms of control over the 0.8 mile stretch.” The court acknowledged that “the federal government did fund an environmental study of a potential bypass around Eufaula about a decade ago” but found this was not enough to federalize the project: “Just because the federal government once offered to fund a segment of a highway does not mean that an alternative plan, proposed ten years later, constitutes a major federal action, especially when there is minimal federal-government involvement in the new plan.” Part of a Larger Project. Third, the court considered “whether the segment at issue forms part of a larger coherent project.” The court noted that the project did have some connections to other widening projects on Highway 431, but held that “this project is more discrete than those found to be major federal projects in other cases. It did not receive a single source of funding at one time, but has been funded in parts. These discrete parts have also occurred over nearly four decades rather than within a short time span. It is also not a bypass or a wholly new project, but rather improvements on an existing road.” After weighing these factors, the court held that the North Eufala Avenue had not been federalized, and therefore ADOT was free to proceed with the project without completing any federal environmental review. The court acknowledged that the plaintiffs “present a strong argument that this historic area should not be put in jeopardy.” But the court concluded that, because this is a non-federal project, the policy question of how to balance transportation and historic preservation concerns “should thus be resolved at the local level—that is, between the State of Alabama and the City of Eufaula.” Because the court found that there was no federal action, it denied the motion for a TRO.
File Attachment
Download the decision